TEMPORARY ROADWAY MATS FOR INFRASTRUCTURE PROJECTS

A substation build, a rail-adjacent upgrade or a multi-stage utilities project can span a site measured in hectares, yet in any given week only a fraction of that ground may actually be carrying traffic.

Temporary roadway mats for infrastructure projects only need to cover the areas in use at each stage. Planning the requirement around the full site footprint from the outset can mean bringing in more matting than the job needs at that point.

But plan too narrowly and the opposite problem appears when the working area moves and the next section isn’t covered.

What actually changes stage to stage

No two parts of an infrastructure job move at the same pace. Access may shift as work finishes in one part of the site and moves into the next. Deliveries might need to reach a section that wasn’t accessible in phase one because the access route itself didn’t exist yet. Plant working close to the site boundary in month two could be working in the middle of it by month six.

Ground conditions on the next section won’t necessarily be the same as those beneath the roadway already in use. Traffic type and volume shift too, early groundworks and later plant movements don’t put the same load through the same ground.

The programme needs to show where mats can genuinely be released for reuse and where they’ll remain tied up in a live section. That distinction affects how far the same stock can follow the work and where phased deliveries will be needed to cover the next stage.

Ground conditions can create problems at any stage of the project

The awkward sections aren’t always where you expected them to be when the roadway was first planned. Ground that was firm in summer can become difficult in winter, while wet patches, uneven verges or changes to the route can create problems elsewhere. Terrain throws up its own problems too. A route that has to cross a bank, work round a watercourse or climb a gradient needs thinking about differently to a stretch of open, level ground.

Sometimes it’s only a short stretch. A delivery route might need to cross an area that wasn’t expected to carry traffic, or access may need to extend into a new part of the site. In that case, it can make more sense to deal with that section separately, using temporary roadway or temporary access mats where they’re needed, rather than changing the wider layout.

Building the supply plan stage by stage

Where the programme gives us enough visibility, we can plan when mats are likely to be released from one area. That tells us where they can be reused and when we’ll need to bring in additional stock instead. That helps keep the quantity on site closer to what the project actually needs as it progresses.

Just as importantly, the supply plan needs some flexibility. Access routes move, dates slip, ground conditions change and sections can come into use earlier than expected. We’re used to responding quickly when that happens, whether that means bringing in additional mats, changing the specification or adjusting the next delivery.

The aim is to plan as much as we can early, without assuming the job will stay exactly as planned.

Planning temporary roadway mats for infrastructure projects